Software Engineering | Software Project Management Plan (SPMP)

Once project designing is complete, project managers document their plans during a software package Project Management set up (SPMP) document. The SPMP document ought to discuss an inventory of various things that are mentioned below.

This list will be used as a doable organization of the SPMP document. Organization of the software package Project Management set up (SPMP) document.

  1. Introduction:
    • Objectives
    • Major Functions
    • Performance Issues
    • Management and Technical Constraints
  2. Project Estimates:
    • Historical Data Used
    • Estimation Techniques Used
    • Effort, Resource, Cost, and Project Duration Estimates
  3. Schedule:
    • Work Breakdown Structure
    • Task Network Representation
    • Gantt Chart Representation
    • PERT Chart Representation
  4. Project Resources:
    • People
    • Hardware and Software
    • Special Resources
  5. Staff Organization:
    • Team Structure
    • Management Reporting
  6. Risk Management Plan:
    • Risk Analysis
    • Risk Identification
    • Risk Estimation
    • Risk Abatement Procedures
  7. Project Tracking and Control Plan
  8. Miscellaneous Plans:
    • Process Tailoring
    • Quality Assurance Plan
    • Configuration Management Plan
    • Validation and Verification
    • System Testing Plan
    • Delivery, Installation, and Maintenance Plan


My Personal Notes arrow_drop_up

Check out this Author's contributed articles.

If you like GeeksforGeeks and would like to contribute, you can also write an article using contribute.geeksforgeeks.org or mail your article to contribute@geeksforgeeks.org. See your article appearing on the GeeksforGeeks main page and help other Geeks.

Please Improve this article if you find anything incorrect by clicking on the "Improve Article" button below.




Article Tags :

Be the First to upvote.


Please write to us at contribute@geeksforgeeks.org to report any issue with the above content.