A person employed a group of 20 men for a construction job. These 20 men working 8 hours a day can complete the job in 28 days. The work started on time but after 18 days, it was observed that two thirds of the work was still pending. To avoid penalty and complete the work on time, the employer had to employ more men and also increase the working hours to 9 hours a day. Find the additional number of men employed if the efficiency of all men is same. (A) 40 (B) 44 (C) 64 (D) 80

Answer: (B)

Explanation: Let the total work be 3 units and additional men employed after 18 days be ‘x’. => Work done in first 18 days by 20 men working 8 hours a day = (1/3) x 3 = 1 unit => Work done in last 10 days by (20 + x) men working 9 hours a day = (2/3) x 3 = 2 unit Here, we need to apply the formula M1 D1 H1 E1 / W1 = M2 D2 H2 E2 / W2, where M1 = 20 men D1 = 18 days H1 = 8 hours/day W1 = 1 unit E1 = E2 = Efficiency of each man M2 = (20 + x) men D2 = 10 days H2 = 9 hours/day W2 = 2 unit   So, we have 20 x 18 x 8 / 1 = (20 + x) x 10 x 9 / 2 => x + 20 = 64 => x = 44 Therefore, additional men employed = 44

Quiz of this Question

Last Updated : 28 Jun, 2021
Like Article
Save Article
Previous
Next
Share your thoughts in the comments
Similar Reads