Assume the following regarding the development of a software system P: - Estimated lines of code of P : 33, 480 LOC - Average productivity for P : 620 LOC per person-month - Number of software developers : 6 - Average salary of a software developer : ` 50,000 per month If E, D and C are the estimated development effort (in person-months), estimated development time (in months), and estimated development cost (in ` Lac) respectively, then (E, D, C) =_________.
(A)
(48, 8, 24)
(B)
(54, 9, 27)
(C)
(60, 10, 30)
(D)
(42, 7, 21)