UGC-NET | UGC NET CS 2014 Dec - III | Question 45

Assume that the software team defines a project risk with 80% probability of occurrence of risk in the following manner : Only 70 percent of the software components scheduled for reuse will be integrated into the application and the remaining functionality will have to be custom developed. If 60 reusable components were planned with average component size as 100 LOC and software engineering cost for each LOC as $ 14, then the risk exposure would be

(A)

$ 25,200

(B)

$ 20,160

(C)

$ 17,640

(D)

$ 15,120

Answer

Please comment below if you find anything wrong in the above post
Feeling lost in the world of random DSA topics, wasting time without progress? It's time for a change! Join our DSA course, where we'll guide you on an exciting journey to master DSA efficiently and on schedule.
Ready to dive in? Explore our Free Demo Content and join our DSA course, trusted by over 100,000 geeks!

Last Updated :
Share your thoughts in the comments