A simple stand - alone software utility is to be developed in ’C’ programming by a team of software experts for a computer running Linux and the overall size of this software is estimated to be 20,000 lines of code. Considering (a, b) = (2.4, 1.05) as multiplicative and exponential factor for the basic COCOMO effort estimation equation and (c, d) = (2.5, 0.38) as multiplicative and exponential factor for the basic COCOMO development time estimation equation, approximately how long does the software project take to complete?

(A)

10.52 months

(B)

11.52 months

(C)

12.52 months

(D)

14.52 months

Answer

Please comment below if you find anything wrong in the above post
Feeling lost in the world of random DSA topics, wasting time without progress? It's time for a change! Join our DSA course, where we'll guide you on an exciting journey to master DSA efficiently and on schedule.
Ready to dive in? Explore our Free Demo Content and join our DSA course, trusted by over 100,000 geeks!

Last Updated :
Share your thoughts in the comments