ISRO | ISRO CS 2007 | Question 43

On a system using non-preemptive scheduling, processes with expected run times of 5, 18, 9 and 12 are in the ready queue. In what order should they be run to minimize wait time?

(A)

5, 12, 9, 18

(B)

5, 9, 12, 18

(C)

12, 18, 9, 5

(D)

9, 12, 18, 5

Answer

Please comment below if you find anything wrong in the above post