Aptitude | Wipro Mock Test | Question 22

Neha and Sandy can do a piece of work in 24 day; Sandy and Tina in 30 days;Tina and Neha in 40 days. If all work together they will complete work  in ___ days

(A)

20

(B)

30

(C)

25

(D)

35

Answer