Consider the following set of jobs to be scheduled for execution on a single CPU system.
Job Arrival Time Size (msec) Priority J1 0 10 2 (Silver) J2 2 8 1 (Gold) J3 3 3 3 (Bronze) J4 10 4 2 (Silver) J5 12 1 3 (Bronze) J6 15 4 1 (Gold)
Which of the following is the correct order for scheduling policies providing the lowest waiting time for this set of jobs?
(A) Non-preemptive SJF
(B) Non-preemptive SJF
(C) Non-preemptive SJF
(D) Non-preemptive SJF Answer: (C)
Explanation: 1. Gantt chart for FCFS scheduling:
Job Arrival Time Size (msec) Priority Turn around time Waiting time J1 0 10 2 (Silver) 0 0 J2 2 8 1 (Gold) 16 8 J3 3 3 3 (Bronze) 18 15 J4 10 4 2 (Silver) 15 11 J5 12 1 3 (Bronze) 14 13 J6 15 4 1 (Gold) 15 11
Average waiting time
= (0 + 8 + 15 + 11 + 13 + 11) / 6 = 9.67
2. Gantt chart for non-preemptive SJF scheduling:
Job Arrival Time Size (msec) Priority Turn around time Waiting time J1 0 10 2 (Silver) 0 0 J2 2 8 1 (Gold) 28 20 J3 3 3 3 (Bronze) 10 7 J4 10 4 2 (Silver) 8 4 J5 12 1 3 (Bronze) 2 1 J6 15 4 1 (Gold) 7 3
Average waiting time
= (0 + 20 + 7 + 4 + 1 + 3) / 6 = 5.83
3. Gantt chart for non-preemptive priority scheduling:
Job Arrival Time Size (msec) Priority Turn around time Waiting time J1 0 10 2 (Silver) 0 0 J2 2 8 1 (Gold) 16 8 J3 3 3 3 (Bronze) 26 23 J4 10 4 2 (Silver) 16 12 J5 12 1 3 (Bronze) 18 17 J6 15 4 1 (Gold) 15 3
Average waiting time
= (0 + 8 + 23 + 12 + 17 + 3) / 6 = 10.5
4. Gantt chart for preemptive priority scheduling:
Job Arrival Time Size (msec) Priority Turn around time Waiting time J1 0 10 2 (Silver) 0 12 J2 2 8 1 (Gold) 8 0 J3 3 3 3 (Bronze) 26 3 J4 10 4 2 (Silver) 16 12 J5 12 1 3 (Bronze) 18 17 J6 15 4 1 (Gold) 4 0
Average waiting time
= (12 + 0 + 3 + 12 + 17 + 0) / 6 = 7.33
Therefore, Non-preemptive SJF
So, option (C) is correct.