Which one from the following is highly associated activity of project planning?

(A)



Keep track of the project progress.

(B)



Compare actual and planned progress and costs.

(C)

Identify the activities, milestones and deliverables produced by a project.

(D)

Both (2) and (3).


Answer: (C)
Explanation:

Identifying project activities, milestones, and deliverables is crucial in project planning. Activities outline tasks, milestones mark progress checkpoints, and deliverables define project outcomes. This process establishes a clear project scope, aids in resource allocation, and ensures effective time and cost management, ultimately contributing to project success.