UGC-NET | UGC NET CS 2015 Jun – II | Question 45
Which one from the following is highly associated activity of project planning?
(A) Keep track of the project progress.
(B) Compare actual and planned progress and costs.
(C) Identify the activities, milestones and deliverables produced by a project.
(D) Both (2) and (3).
Answer: (C)
Explanation: