ISRO | ISRO CS 2015 | Question 59

If in a software project the number of user input, user output, enquiries, files and external interfaces are (15, 50, 24, 12, 8), respectively, with complexity average weighing factor. The productivity if effort = 70 percent-month is
(A) 110.54
(B) 408.74
(C) 304.78
(D) 220.14

Answer: (B)
Explanation:
Quiz of this Question