If in a software project the number of user input, user output, enquiries, files and external interfaces are (15, 50, 24, 12, 8), respectively, with complexity average weighing factor. The productivity if effort = 70 percent-month is
(A) 110.54
(B) 408.74
(C) 304.78
(D) 220.14


Answer: (B)

Explanation:

Quiz of this Question
Please comment below if you find anything wrong in the above post