A software organization has been assessed at SEI CMM Level 4. Which of the following does the organization need to practice beside Process Change Management and Technology Change Management in order to achieve Level 5 ?
(A) Defect Detection
(B) Defect Prevention
(C) Defect Isolation
(D) Defect Propagation

Answer: (B)
Explanation: Defect Prevention is the organization need to practice beside Process Change Management and Technology Change Management in order to achieve Level 5.