Match the 5 CMM Maturity levels/CMMI staged representations in List- I with their characterizations in List-II
List – I | List – II | ||||
(a) Initial | (i)Processes are improved quantitatively and continually. | ||||
(b)Repeatable | (ii) The plan for a project comes from a template for plans. | ||||
(c)Defined | (iii)The plan uses processes that can be measured quantitatively. |
||||
(d)Managed | (iv)There may not exist a plan or it may be abandoned. | ||||
(e)Optimizing | (v)There’s a plan and people stick to it. | ||||
(a) | (b) | (c) | (d) | ||
(1) | (iv) | (v) | (i) | (iii) | (iv) |
(2) | (i) | (ii) | (iv) | (v) | (iii) |
(3) | (v) | (iv) | (ii) | (iii | (i) |
(4) | (iv) | (v) | (ii) | (iii) | (i) |
(A) (1)
(B) (2)
(C) (3)
(D) (4)
Answer: (D)
Explanation:
So, option (D) is correct.