Match the 5 CMM Maturity levels/CMMI staged representations in List- I with their characterizations in List-II



codes:

List – I List – II
(a) Initial (i)Processes are improved quantitatively and continually.
(b)Repeatable (ii) The plan for a project comes from a template for plans.
(c)Defined (iii)The plan uses processes that can be measured
quantitatively.
(d)Managed (iv)There may not exist a plan or it may be abandoned.
(e)Optimizing (v)There’s a plan and people stick to it.
(a) (b) (c) (d)
(1) (iv) (v) (i) (iii) (iv)
(2) (i) (ii) (iv) (v) (iii)
(3) (v) (iv) (ii) (iii (i)
(4) (iv) (v) (ii) (iii) (i)


(A) (1)
(B) (2)
(C) (3)
(D) (4)

Answer: (D)
Explanation:



  • CMM Maturity levels/CMMI at Initial stage there may not exist a plan or it may be abandoned
  • In repeatable stage thers is a plan and people are stick to it.
  • At Defined stage the plan for a project comes from a template for plans.
  • At Managed stage the plan uses processes that can be measured quantitatively
  • Optimizing stage processes are improved quantitatively and continually.
  • So, option (D) is correct.