UGC-NET | UGC NET CS 2014 Dec – II | Question 41

__________ are applied throughout the software process.
(A) Framework activities
(B) Umbrella activities
(C) Planning activities
(D) Construction activities

Answer: (B)
Explanation: Umbrella activities are applied throughout the software process.
Umbrella activities include:

  • Document Preparation and Production.
  • Configuration Management.
  • Project Tracking and Control.
  • Quality Assurance.
  • Formant Technical Review.
  • Reusability Management.
  • Measurement.
  • Risk Management

    So, option (B) is correct.