Open In App

GATE | Gate IT 2007 | Question 4

In the Spiral model of software development, the primary determinant in selecting activities in each iteration is
(A) Iteration size
(B) Cost
(C) Adopted process such as Rational Unified Process or Extreme Programming
(D) Risk

Answer: (D)
Explanation: Spiral model is used to discover all risks associated as early as possible.
Quiz of this Question

Article Tags :