Consider n jobs J
1, J
2,……J
n such that job J
i has execution time t
i and a non-negative integer weight w
i. The weighted mean completion time of the jobs is defined to be
, where T
i is the completion time of job J
i. Assuming that there is only one processor available, in what order must the jobs be executed in order to minimize the weighted mean completion time of the jobs?
(A) Non-decreasing order of t
i(B) Non-increasing order of w
i(C) Non-increasing order of w
it
i(D) None-increasing order of w
i/t
iAnswer:(D)Explanation:Quiz of this Question