Work and Wages Read Discuss Courses If a person can do a piece of work in ‘n’ days, then in one day, the person will do ‘1/n’ work. Conversely, if the person does ‘1/n’ work in one day, the person will require ‘n’ days to finish the work … More on Work and Wages Work and Wages Please wait while the activity loads. If this activity does not load, try refreshing your browser. Also, this page requires javascript. Please visit using a browser with javascript enabled. If loading fails, click here to try again Question 1Two friends A and B were employed to do a work. Initial deadline was fixed at 24 days. Both started working together but after 20 days, A left the work and the whole work took 30 days to complete. In how much time can B alone can do the work?40506070Work and Wages Discuss itQuestion 1-Explanation: Let the total work be 24 units. It is given that A and B together can do the work in 24 days. => Combined efficiency of A and B = 24/24 = 1 unit / day => Work done in 20 days = 20 units => Work left = 24 - 20 = 4 units Now, this remaining 4 units of work was done by B alone in 10 days. => Efficiency of B = 4/10 = 0.4 Therefore, time required by B alone to do the work = 24/0.4 = 60 daysQuestion 2A and B took a job to be completed in 20 days. They started working together and after 12 days, C joined them and the whole job finished in 15 days. How much time would C require to complete the job if only C was hired?1512108Work and Wages Discuss itQuestion 2-Explanation: Let the total job be 20 units. It is given that A and B took the job to be completed in 20 days. => Combined efficiency of A and B = 20/20 = 1 unit / day Now, job done in 12 days = 12 units => Job Left = 8 units Now, this remaining 8 units of job has been done by all A, B and C together. Let the efficiency of C be 'x'. => Combined efficiency of A, B and C = 1+x units/ day Now, with this efficiency, the job got completed in 3 more days. => Job done in 3 days = 3 x (1+x) = 8 units => x = 5/3 Therefore, efficiency of C = x = 5/3 units / day Hence, time required by C alone to do the job = 20/(5/3) = 12 daysQuestion 3Three people A, B and C working individually can finish a job in 10, 12 and 20 days respectively. They decided to work together but after 2 days, A left the work and after another one day, B also left work. If they got two lacs collectively for the entire work, find the difference of the highest and lowest share.70000600001000020000Work and Wages Discuss itQuestion 3-Explanation: Let the total work be LCM(10, 12, 20) = 60 units => Efficiency of A = 60/10 = 6 units / day => Efficiency of B = 60/12 = 5 units / day => Efficiency of C = 60/20 = 3 units / day Since the number of working days are different for each person, the share of each will be calculated in the ratio of the units of work done. Now, A works for 2 days and B works for 3 days. => Work done by A = 2 x 6 = 12 units => Work done by B = 3 x 5 = 15 units => Work done by C = 60 - 12 - 15 = 33 units Therefore, ratio of work done = 12:15:33 = 4:5:11 So, A's share = (4/20) x 2,00,000 = Rs 40,000 B's share = (5/20) x 2,00,000 = Rs 50,000 C's share = (11/20) x 2,00,000 = Rs 1,10,000 Therefore, difference of the highest and lowest share = Rs 1,10,000 - 40,000 = Rs 70,000Question 4A alone and B alone can do a work in respectively 18 and 8 days more than both working together. Find the number of days required if both work together. 1281636Work and Wages Discuss itQuestion 4-Explanation: Let the time required to complete the work by A and B together = n days => Time required by A alone = n + 18 days => Time required by B alone = n + 8 days Therefore, n2 = 18 x 8 = 144 => n = 12 Hence, A and B require 12 days to complete the work if they work together.Question 5Three friends A, B and C are employed to make pastries in a bakery. Working individually, they can make 60, 30 and 40 pastries respectively in an hour. They decided to work together but due to lack of resources, they had to work on shifts of 30 minutes. Find the time taken to make 185 pastries. 4 hours3 hours 45 minutes4 hours 15 minutes5 hoursWork and Wages Discuss itQuestion 5-Explanation: It is given that A, B and C make 60, 30 and 40 pastries respectively in an hour. => In 30 minutes, they will make 30, 15 and 20 pastries respectively. So, in one cycle of 1 hour 30 minutes where each works for 30 minutes, pastries made = 30 + 15 + 20 = 65 Now, in 2 cycles (3 hours), 130 pastries would be made. In the next 30 minutes, A would make 30 pastries. So, total time elapsed = 3 hours 30 minutes and pastries made = 130 + 30 = 160 In the next 30 minutes, B would make 15 pastries. So, total time elapsed = 4 hours and pastries made = 160 + 15 = 175 In the next 15 minutes, C would make 10 pastries. So, total time elapsed = 4 hours 15 minutes and pastries made = 175 + 10 = 185 Therefore, total time taken = 4 hours 15 minutesQuestion 6A person employed a group of 20 men for a construction job. These 20 men working 8 hours a day can complete the job in 28 days. The work started on time but after 18 days, it was observed that two thirds of the work was still pending. To avoid penalty and complete the work on time, the employer had to employ more men and also increase the working hours to 9 hours a day. Find the additional number of men employed if the efficiency of all men is same.40446480Work and Wages Discuss itQuestion 6-Explanation: Let the total work be 3 units and additional men employed after 18 days be 'x'. => Work done in first 18 days by 20 men working 8 hours a day = (1/3) x 3 = 1 unit => Work done in last 10 days by (20 + x) men working 9 hours a day = (2/3) x 3 = 2 unit Here, we need to apply the formula M1 D1 H1 E1 / W1 = M2 D2 H2 E2 / W2, where M1 = 20 men D1 = 18 days H1 = 8 hours/day W1 = 1 unit E1 = E2 = Efficiency of each man M2 = (20 + x) men D2 = 10 days H2 = 9 hours/day W2 = 2 unit So, we have 20 x 18 x 8 / 1 = (20 + x) x 10 x 9 / 2 => x + 20 = 64 => x = 44 Therefore, additional men employed = 44Question 76 men and 10 women were employed to make a road 360 km long. They were able to make 150 kilometres of road in 15 days by working 6 hours a day. After 15 days, two more men were employed and four women were removed. Also, the working hours were increased to 7 hours a day. If the daily working power of 2 men and 3 women are equal, find the total number of days required to complete the work. 19353450Work and Wages Discuss itQuestion 7-Explanation: We are given that the daily working power of 2 men and 3 women are equal. => 2 Em = 3 Ew => Em / Ew = 3/2, where 'Em' is the efficiency of 1 man and 'Ew' is the efficiency of 1 woman. Therefore, ratio of efficiency of man and woman = 3 : 2. If 'k' is the constant of proportionality, Em = 3k and Ew = 2k. Here, we need to apply the formula ∑(Mi Ei) D1 H1 / W1 = ∑(Mj Ej) D2 H2 / W2, where ∑(Mi Ei) = (6 x 3k) + (10 x 2k) ∑(Mj Ej) = (8 x 3k) + (6 x 2k) D1 = 15 days D2 = Number of days after increasing men and reducing women H1 = 6 hours H2 = 7 hours W1 = 150 km W2 = 210 km So, we have 38k x 15 x 6 / 150 = 36k x D2 x 7 / 210 => 38k x 6 = 12k x D2 => D2 = 19 days Therefore, total days required to complete the work = 15 + 19 = 34 daysQuestion 8A stadium was to be built in 1500 days. The contractor employed 200 men, 300 women and 750 robotic machines. After 600 days, 75% of the work was still to be done. Fearing delay, the contractor removed all women and 500 robotic machines. Also, he employed some more men having the same efficiency as earlier employed men. This led to a speedup in work and the stadium got built 50 days in advance. Find the additional number of men employed if in one day, six men, ten women and fifteen robotic machines have same work output. 1100134013001140Work and Wages Discuss itQuestion 8-Explanation: Let the total work be 4 units. => Work done in first 600 days = 25% of 4 = 1 unit => Work done in next 850 days = 75% of 4 = 3 unit Also, we are given that the daily work output of 6 men, 10 women and 15 robotic machines are same. => 6 Em = 10 Ew = 15 Er => Em : Ew : Er = 5 : 3 : 2, where 'Em' is the efficiency of 1 man, 'Ew' is the efficiency of 1 woman and 'Er' is the efficiency of 1 robotic machine. Therefore, ratio of efficiency of man, woman and robotic machine = 5:3:2. If 'k' is the constant of proportionality, Em = 5k, Ew = 3k and Er = 2k. Here, we need to apply the formula ∑(Mi Ei) D1 H1 / W1 = ∑(Mj Ej) D2 H2 / W2, where ∑(Mi Ei) = (200 x 5k) + (300 x 3k) + (750 x 2k) ∑(Mj Ej) = (200 x 5k) + (m x 5k) + (250 x 2k), where 'm' is the additional men employed D1 = 600 days D2 = 850 days H1 = H2 = Daily working hours W1 = 1 unit W2 = 3 units So, we have 3400k x 600 / 1 = (1500 + 5m)k x 850 / 3 => 3400k x 1800 = (1500 + 5m)k x 850 => 1500 + 5m = 7200 => 5m = 5700 => m = 1140 Therefore, additional men employed = 1140Question 93 men and 4 women can complete a work in 10 days by working 12 hours a day. 13 men and 24 women can do the same work by working same hours a day in 2 days. How much time would 12 men and 1 women working same hours a day will take to complete the whole work?46810Work and Wages Discuss itQuestion 9-Explanation: Here, we need to apply the formula ∑(Mi Ei) D1 H1 / W1 = ∑(Mj Ej) D2 H2 / W2, where ∑(Mi Ei) = (3 x m) + (4 x w) ∑(Mj Ej) = (13 x m) + (24 x w), where 'm' is the efficiency of each man and 'w' is the efficiency of each woman D1 = 10 days D2 = 2 days H1 = 12 hours H2 = 12 hours W1 = W2 = Work to be done So, we have (3m + 4w) x 10 x 12 = (13m + 24w) x 2 x 12 => 15m + 20w = 13m + 24w => 2m = 4w => m = 2w => m : w = 2 : 1 Therefore, ratio of efficiency of man and woman = 2 : 1 If the constant of proportionality be 'k', Efficiency of each man = m = 2k Efficiency of each woman = w = k Now, we re-apply the same formula. ∑(Mi Ei) D1 H1 / W1 = ∑(Mj Ej) D2 H2 / W2, where ∑(Mi Ei) = (3 x m) + (4 x w) ∑(Mj Ej) = (12 x m) + (1 x w) D1 = 10 days D2 = Days requires by 12 men and 1 woman H1 = 12 hours H2 = 12 hours W1 = W2 = Work to be done So, we have (3m + 4w) x 10 x 12 = (12m + w) x D2 x 12 => 30m + 40w = (12m + w) x D2 => 60k + 40k = (24k + k) x D2 => 100k = 25k x D2 => D2 = 4 Therefore, 12 men and 1 woman would require 4 days to complete the work.Question 10600 men can make a road in 500 days. They start working together but after every hundred days, 50 men leave the work. Find the total time (in days) it takes to make the road.600550650750Work and Wages Discuss itQuestion 10-Explanation: 600 men can make a road in 500 days. => Total work = 600 x 500 = 3,00,000 units Now, 600 men start working but after every hundred days, 50 men leave the work. => Work done in first 100 days = 600 x 100 = 60,000 units and total work done = 60,000 units => Work done in next 100 days = 550 x 100 = 55,000 units and total work done = 1,15,000 units => Work done in next 100 days = 500 x 100 = 50,000 units and total work done = 1,65,000 units => Work done in next 100 days = 450 x 100 = 45,000 units and total work done = 2,10,000 units => Work done in next 100 days = 400 x 100 = 40,000 units and total work done = 2,50,000 units => Work done in next 100 days = 350 x 100 = 35,000 units and total work done = 2,85,000 units => Work done in next 50 days = 300 x 50 = 15,000 units and total work done = 3,00,000 units Therefore, total time (days) taken to make the road = 650 days 12 There are 15 questions to complete. You have completed questions question Your accuracy is Correct Wrong Partial-Credit You have not finished your quiz. If you leave this page, your progress will be lost. Correct Answer You Selected Not Attempted Final Score on Quiz Attempted Questions Correct Attempted Questions Wrong Questions Not Attempted Total Questions on Quiz Question Details Results Date Score Hint Time allowed minutes seconds Time used Answer Choice(s) Selected Question Text All doneNeed more practice!Keep trying!Not bad!Good work!Perfect! Last Updated : 27 Sep, 2023