The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Java is 50. Estimate the effort (E) required to complete the project using the effort formula of basic COCOMO given below :
E = a(KLOC)b
Assume that the values of a and b are 2.5 and 1.0 respectively.
(A) 25 person months
(B) 75 person months
(C) 62.5 person months
(D) 72.5 person months


Answer: (C)

Explanation: E = a(KLOC)b
a = 2.5 , b = 1.0
LOC / FP = 50
500 FP
So, 50 * 500 = 25000 loc
i.e 25 KLOC
E = 2.5(25)1 = 62.5 person months.
So, option (C) is correct.