Skip to content
Related Articles

Related Articles

Improve Article
Save Article
Like Article

UGC-NET | UGC NET CS 2015 Jun – II | Question 45

  • Last Updated : 08 May, 2018

Which one from the following is highly associated activity of project planning?
(A) Keep track of the project progress.
(B) Compare actual and planned progress and costs.
(C) Identify the activities, milestones and deliverables produced by a project.
(D) Both (2) and (3).


Answer: (C)

Explanation:

Quiz of this Question
Please comment below if you find anything wrong in the above post

My Personal Notes arrow_drop_up
Recommended Articles
Page :

Start Your Coding Journey Now!