Open In App

UGC-NET | UGC NET CS 2014 Dec – III | Question 45

Like Article
Like
Save
Share
Report

Assume that the software team defines a project risk with 80% probability of occurrence of risk in the following manner :
Only 70 percent of the software components scheduled for reuse will be integrated into the application and the remaining functionality will have to be custom developed. If 60 reusable components were planned with average component size as 100 LOC and software engineering cost for each LOC as $ 14, then the risk exposure would be
(A) $ 25,200
(B) $ 20,160
(C) $ 17,640
(D) $ 15,120


Answer: (B)

Explanation: In the application,

Components = 60
Avg LOC = 100
cost of each LOC = 14
Risk Probability = 80 % 

Number of reusable components available = 60
Part of reusable components actually included = 70%
No. of components to be developed from scratch = 30% of 60 = 0.3&60 = 18
Total LOC needed to be written from scratch = 18*100 = 1800
Total cost = 1800*14 = Rs 25200
Probability of occurrence of risk = 80% = 0.8
So, Risk exposure = ( Risk Probability = 0.8 ) x ( Development Cost=25200 ) = 20160

Option (B) is correct.



This explanation is provided by chitrasingla2001.

Quiz of this Question


Last Updated : 06 May, 2020
Like Article
Save Article
Previous
Next
Share your thoughts in the comments
Similar Reads