A, B and C can do a piece of work in 10, 12 and 15 days respectively.They all start the work together but A leaves after the 2 days of work and B leaves 3 days before the work is completed.Find the number of days the work completed.

(A)

4 days

(B)

7 days

(C)

6 days

(D)

9 days



Answer: (B)

Explanation:

Total work done is LCM(10, 12, 15)=60 unit 
A’s efficiency = 60/10= 6 
B’s efficiency = 60/12= 5 
C’s efficiency = 60/15= 4 
First two days all work together So, the work completed in first two days= 15 x 2 = 30 unit 
Remaining work= 60 – 30 = 30 unit 
If B completes 3 day work also = 3 x 5 = 15 unit 
Total work remaining= 30 + 15 = 45 unit 
Number of days B and C works= 45/9=5 
Total number of days to complete the work = 2 + 5 = 7 days.


Quiz of this Question
Please comment below if you find anything wrong in the above post


Last Updated : 03 May, 2019
Like Article
Save Article
Previous
Next
Share your thoughts in the comments
Similar Reads