Open In App

ISRO | ISRO CS 2007 | Question 43

Like Article
Like
Save
Share
Report

On a system using non-preemptive scheduling, processes with expected run times of 5, 18, 9 and 12 are in the ready queue. In what order should they be run to minimize wait time?
(A) 5, 12, 9, 18
(B) 5, 9, 12, 18
(C) 12, 18, 9, 5
(D) 9, 12, 18, 5


Answer: (B)

Explanation: The processes should execute in SJF manner to get the lowest waiting time. So, the order should be 5, 9, 12, 18.

Option (B) is correct.

Quiz of this Question


Last Updated : 27 Jun, 2018
Like Article
Save Article
Previous
Next
Share your thoughts in the comments
Similar Reads