ISRO | ISRO CS 2007 | Question 12
Consider a job scheduling problem with 4 jobs J1, J2, J3, J4 and with corresponding deadlines: ( d1, d2, d3, d4) = (4, 2, 4, 2). Which of the following is not a feasible schedule without violating any job schedule?
(A) J2, J4, J1, J3
(B) J4, J1, J2, J3
(C) J4, J2, J1, J3
(D) J4, J2, J3, J1
Answer: (B)
Explanation: