Consider a job scheduling problem with 4 jobs J1, J2, J3, J4 and with corresponding deadlines: ( d1, d2, d3, d4) = (4, 2, 4, 2). Which of the following is not a feasible schedule without violating any job schedule?

(A)

J2, J4, J1, J3

(B)

J4, J1, J2, J3

(C)

J4, J2, J1, J3

(D)

J4, J2, J3, J1


Answer: (B)

Explanation:

Option A: 2,2,4,4. No problem.

 Option B: 2,4,2,4. 

The third job in this sequence had to be completed under 2 time units. But it took 3 time units. This isn’t an optimal solution, hence the answer. 

Option C: 2,2,4,4. No problem. 

Option D: 2,2,4,4. No problem.