GATE | Gate IT 2008 | Question 56

  • Last Updated : 28 Jun, 2021

A software project plan has identified ten tasks with each having dependencies as given in the following table:

Task        Depends On
T1                 –
T2                T1
T3                T1
T4                T1
T5                T2
T6                T3
T7                T3, T4
T8               T4
T9               T5, T7, T8
T10             T6, T9
Answer the following questions:

(Q1) What is the maximum number of tasks that can be done concurrently?
(Q2) What is the minimum time required to complete the project, assuming that each task requires one time unit and there is no restriction on the number of tasks that can be done in parallel ?
(A) 5, 5
(B) 4, 5
(C) 5, 4
(D) 4, 4


Answer: (B)

Explanation: 2008_58_sol

Quiz of this Question

Attention reader! Don’t stop learning now.  Practice GATE exam well before the actual exam with the subject-wise and overall quizzes available in GATE Test Series Course.

Learn all GATE CS concepts with Free Live Classes on our youtube channel.

My Personal Notes arrow_drop_up
Recommended Articles
Page :