GATE | Gate IT 2008 | Question 56

A software project plan has identified ten tasks with each having dependencies as given in the following table: Task        Depends On T1                 - T2                T1 T3                T1 T4                T1 T5                T2 T6                T3 T7                T3, T4 T8               T4 T9               T5, T7, T8 T10             T6, T9 Answer the following questions: (Q1) What is the maximum number of tasks that can be done concurrently? (Q2) What is the minimum time required to complete the project, assuming that each task requires one time unit and there is no restriction on the number of tasks that can be done in parallel ?

(A)

5, 5

(B)

4, 5

(C)

5, 4

(D)

4, 4

Answer

Please comment below if you find anything wrong in the above post
Feeling lost in the world of random DSA topics, wasting time without progress? It's time for a change! Join our DSA course, where we'll guide you on an exciting journey to master DSA efficiently and on schedule.
Ready to dive in? Explore our Free Demo Content and join our DSA course, trusted by over 100,000 geeks!

Last Updated :
Share your thoughts in the comments