GATE | GATE IT 2006 | Question 84

Like Article
Like
Save
Share
Report

A software project has four phases P1, P2, P3 and P4. Of these phases, P1 Is the first one and needs to be completed before any other phase can commence. Phases P2 and P3 can be executed in parallel. Phase P4 cannot commence until both P2 and P3 are completed. The optimistic, most likely, and pessimistic estimates of the phase completion times in days, for Pl, P2, P3 and P4 are, respectively, (11, 15, 25), (7, 8, 15), (8, 9, 22), and (3, 8, 19).

The costs (in Rupees per day) of crashing the expected phase completion times for the four phases, respectively, are 100, 2000, 50, and 1000. Assume that the expected phase completion times of the phases cannot be crashed below their respective most likely completion times. The minimum and the maximum amounts (in Rupees) that can be spent on crashing so that ALL paths are critical are, respectively.
(A) 100 and 1000
(B) 100 and 1200
(C) 150 and 1200
(D) 200 and 2000


Answer: (D)

Explanation: Critical task is the one on longest path intermediate task:P3

Quiz of this Question
Please comment below if you find anything wrong in the above post


Last Updated : 28 Jun, 2021
Like Article
Save Article
Previous
Next
Share your thoughts in the comments
Similar Reads