To carry out white box testing of a program, its flow chart representation is obtained as shown in the figure below:cc

 

For basis path based testing of this program, its cyclomatic complexity is
(A) 5
(B) 4
(C) 3
(D) 2


Answer: (C)

Explanation:  

N(nodes) = 9

E(edges) = 10

Cyclomatic Complexity = E – N + 2P

= 10 -9 + 2*1

= 3