Given the intervals [(1, 4), (3, 6), (5, 7), (8, 9)], what would be the output of calling a function that solves the Job Scheduling Algorithm?

(A)

[(1, 4), (5, 7), (8, 9)]

(B)

 [(1, 4), (3, 6), (8, 9)]

(C)

 [(1, 4), (3, 6)]

(D)

 [(1, 4), (3, 6), (5, 7)]



Answer: (C)

Explanation: