GATE | GATE CS 2011 | Question 65

A company needs to develop a strategy for software product development for which it has a choice of two programming languages L1 and L2. The number of lines of code (LOC) developed using L2 is estimated to be twice the LOC developed with Ll. The product will have to be maintained for five years. Various parameters for the company are given in the table below.
Parameter Language L1 Language L2
Man years needed for development LOC/10000 LOC/10000
Development cost per man year Rs. 10,00,000 Rs. 7,50,000
Maintenance time 5 years 5 years
Cost of maintenance per year Rs. 1,00,000 Rs. 50,000
Total cost of the project includes cost of development and maintenance. What is the LOC for L1 for which the cost of the project using L1 is equal to the cost of the project using L2?

(A)

4000

(B)

5000

(C)

4333

(D)

4667

Answer

Please comment below if you find anything wrong in the above post
Feeling lost in the world of random DSA topics, wasting time without progress? It's time for a change! Join our DSA course, where we'll guide you on an exciting journey to master DSA efficiently and on schedule.
Ready to dive in? Explore our Free Demo Content and join our DSA course, trusted by over 100,000 geeks!

Last Updated :
Share your thoughts in the comments