GATE | GATE CS 2010 | Question 64

  • Last Updated : 28 Jun, 2021

5 skilled workers can build a wall in 20 days: 8 semi-skilled workers can build a wall in 25 days; 10 unskilled workers can build a wall in 30 days. If a team has 2 skilled, 6 semi-skilled and 5 unskilled workers, how long will it take to build the wall?
(A) 20
(B) 10
(C) 16
(D) 15


Answer: (D)

Explanation: 5 skilled workers can build a wall in 20 days
1 skilled worker can build the same wall in 100 days
Capacity of each skilled worker is 1/100

8 semi-skilled workers can build a wall in 25 days
1 semi-skilled worker can build the same wall in 200 days
Capacity of each semi-skilled worker is 1/200

Capacity of 1 unskilled worker is 1/300

Capacity of 2 skilled + 6 semi-skilled + 5 unskilled workers is 2(1/100) + 6(1/200) + 5/300
= 1/15


Quiz of this Question

Attention reader! Don’t stop learning now.  Practice GATE exam well before the actual exam with the subject-wise and overall quizzes available in GATE Test Series Course.

Learn all GATE CS concepts with Free Live Classes on our youtube channel.

My Personal Notes arrow_drop_up
Recommended Articles
Page :