What is the appropriate pairing of items in the two columns listing various activities encountered in a software life cycle?

P. Requirements Capture	 1.Module Development and Integration
Q. Design	         2.Domain Analysis
R. Implementation	 3.Structural and Behavioral Modeling
S. Maintenance	         4.Performance Tuning

(A) P-3, Q-2, R-4, S-1
(B) P-2, Q-3, R-1, S-4
(C) P-3, Q-2, R-1, S-4
(D) P-2, Q-3, R-4, S-1


Answer: (B)

Explanation: Module Development and Integration is clearly implementation work
Performance Tuning is clearly maintenance work
Domain Analysis is clearly Requirements Capture