Aptitude | GATE CS 1998 | Question 81
Answer the following:
a. Four jobs are waiting to be run. Their expected run times are 6, 3, 5 and x. In what order should they be run to minimize the average response time?
b. Write a concurrent program using par begin – par end to represent the precedence graph shown below.
Answer:
Explanation:
Quiz of this Question
Please comment below if you find anything wrong in the above post
Recommended Posts:
- Aptitude | GATE CS 1998 | Question 59
- Aptitude | GATE CS 1998 | Question 67
- Aptitude | GATE CS 1998 | Question 68
- Aptitude | GATE CS 1998 | Question 69
- Aptitude | GATE CS 1998 | Question 11
- Aptitude | GATE CS 1998 | Question 70
- Aptitude | GATE CS 1998 | Question 71
- Aptitude | GATE CS 1998 | Question 10
- Aptitude | GATE CS 1998 | Question 9
- Aptitude | GATE CS 1998 | Question 8
- Aptitude | GATE CS 1998 | Question 7
- Aptitude | GATE CS 1998 | Question 6
- Aptitude | GATE CS 1998 | Question 5
- Aptitude | GATE CS 1998 | Question 66
- Aptitude | GATE CS 1998 | Question 60