Consider the following Jobs with their deadline and profit:
Job |
Deadline |
Profit |
a |
2 |
37 |
b |
3 |
50 |
c |
1 |
37 |
d |
4 |
60 |
e |
3 |
50 |
f |
2 |
80 |
Which of the following is not correct profit sequence order for given jobs with respective profit and deadlines?
(A) b, f, e, d
(B) f, d, e, b
(C) e, f, b, d
(D) None of these
Answer: (B)
Explanation: Since maximum deadline is 4, so we can choose 4 jobs only. For maximum profit sequence of given Job sequence:
or
So, f, d, e, b is not correct profit sequence order for given jobs with respective profit and deadlines.
Option (B) is true.