Work and Wages

  • If a person can do a piece of work in ‘n’ days, then in one day, the person will do ‘1/n’ work. Conversely, if the person does ‘1/n’ work in one day, the person will require ‘n’ days to finish the work … More on Work and Wages

Question 1
Two friends A and B were employed to do a work. Initial deadline was fixed at 24 days. Both started working together but after 20 days, A left the work and the whole work took 30 days to complete. In how much time can B alone can do the work?
Cross
40
Cross
50
Tick
60
Cross
70


Question 1-Explanation: 
Let the total work be 24 units. It is given that A and B together can do the work in 24 days. => Combined efficiency of A and B = 24/24 = 1 unit / day => Work done in 20 days = 20 units => Work left = 24 - 20 = 4 units Now, this remaining 4 units of work was done by B alone in 10 days. => Efficiency of B = 4/10 = 0.4 Therefore, time required by B alone to do the work = 24/0.4 = 60 days
Question 2
A and B took a job to be completed in 20 days. They started working together and after 12 days, C joined them and the whole job finished in 15 days. How much time would C require to complete the job if only C was hired?
Cross
15
Tick
12
Cross
10
Cross
8


Question 2-Explanation: 
Let the total job be 20 units. It is given that A and B took the job to be completed in 20 days. => Combined efficiency of A and B = 20/20 = 1 unit / day Now, job done in 12 days = 12 units => Job Left = 8 units Now, this remaining 8 units of job has been done by all A, B and C together. Let the efficiency of C be \'x\'. => Combined efficiency of A, B and C = 1+x units/ day Now, with this efficiency, the job got completed in 3 more days. => Job done in 3 days = 3 x (1+x) = 8 units => x = 5/3 Therefore, efficiency of C = x = 5/3 units / day Hence, time required by C alone to do the job = 20/(5/3) = 12 days
Question 3
Three people A, B and C working individually can finish a job in 10, 12 and 20 days respectively. They decided to work together but after 2 days, A left the work and after another one day, B also left work. If they got two lacs collectively for the entire work, find the difference of the highest and lowest share.
Tick
70000
Cross
60000
Cross
10000
Cross
20000


Question 3-Explanation: 
Let the total work be LCM(10, 12, 20) = 60 units => Efficiency of A = 60/10 = 6 units / day => Efficiency of B = 60/12 = 5 units / day => Efficiency of C = 60/20 = 3 units / day Since the number of working days are different for each person, the share of each will be calculated in the ratio of the units of work done. Now, A works for 2 days and B works for 3 days. => Work done by A = 2 x 6 = 12 units => Work done by B = 3 x 5 = 15 units => Work done by C = 60 - 12 - 15 = 33 units Therefore, ratio of work done = 12:15:33 = 4:5:11 So, A\'s share = (4/20) x 2,00,000 = Rs 40,000 B\'s share = (5/20) x 2,00,000 = Rs 50,000 C\'s share = (11/20) x 2,00,000 = Rs 1,10,000 Therefore, difference of the highest and lowest share = Rs 1,10,000 - 40,000 = Rs 70,000
Question 4
A alone and B alone can do a work in respectively 18 and 8 days more than both working together. Find the number of days required if both work together.
Tick
12
Cross
8
Cross
16
Cross
36


Question 4-Explanation: 
Let the time required to complete the work by A and B together = n days => Time required by A alone = n + 18 days => Time required by B alone = n + 8 days Therefore, n2 = 18 x 8 = 144 => n = 12 Hence, A and B require 12 days to complete the work if they work together.
Question 5
Three friends A, B and C are employed to make pastries in a bakery. Working individually, they can make 60, 30 and 40 pastries respectively in an hour. They decided to work together but due to lack of resources, they had to work on shifts of 30 minutes. Find the time taken to make 185 pastries.
Cross
4 hours
Cross
3 hours 45 minutes
Tick
4 hours 15 minutes
Cross
5 hours


Question 5-Explanation: 
It is given that A, B and C make 60, 30 and 40 pastries respectively in an hour. => In 30 minutes, they will make 30, 15 and 20 pastries respectively. So, in one cycle of 1 hour 30 minutes where each works for 30 minutes, pastries made = 30 + 15 + 20 = 65 Now, in 2 cycles (3 hours), 130 pastries would be made. In the next 30 minutes, A would make 30 pastries. So, total time elapsed = 3 hours 30 minutes and pastries made = 130 + 30 = 160 In the next 30 minutes, B would make 15 pastries. So, total time elapsed = 4 hours and pastries made = 160 + 15 = 175 In the next 15 minutes, C would make 10 pastries. So, total time elapsed = 4 hours 15 minutes and pastries made = 175 + 10 = 185 Therefore, total time taken = 4 hours 15 minutes
Question 6
A person employed a group of 20 men for a construction job. These 20 men working 8 hours a day can complete the job in 28 days. The work started on time but after 18 days, it was observed that two thirds of the work was still pending. To avoid penalty and complete the work on time, the employer had to employ more men and also increase the working hours to 9 hours a day. Find the additional number of men employed if the efficiency of all men is same.
Cross
40
Tick
44
Cross
64
Cross
80


Question 6-Explanation: 
Let the total work be 3 units and additional men employed after 18 days be \'x\'. => Work done in first 18 days by 20 men working 8 hours a day = (1/3) x 3 = 1 unit => Work done in last 10 days by (20 + x) men working 9 hours a day = (2/3) x 3 = 2 unit Here, we need to apply the formula M1 D1 H1 E1 / W1 = M2 D2 H2 E2 / W2, where M1 = 20 men D1 = 18 days H1 = 8 hours/day W1 = 1 unit E1 = E2 = Efficiency of each man M2 = (20 + x) men D2 = 10 days H2 = 9 hours/day W2 = 2 unit   So, we have 20 x 18 x 8 / 1 = (20 + x) x 10 x 9 / 2 => x + 20 = 64 => x = 44 Therefore, additional men employed = 44
Question 7
6 men and 10 women were employed to make a road 360 km long. They were able to make 150 kilometres of road in 15 days by working 6 hours a day. After 15 days, two more men were employed and four women were removed. Also, the working hours were increased to 7 hours a day. If the daily working power of 2 men and 3 women are equal, find the total number of days required to complete the work.
Cross
19
Cross
35
Tick
34
Cross
50


Question 7-Explanation: 
We are given that the daily working power of 2 men and 3 women are equal. => 2 Em = 3 Ew => Em / Ew = 3/2, where \'Em\' is the efficiency of 1 man and \'Ew\' is the efficiency of 1 woman. Therefore, ratio of efficiency of man and woman = 3 : 2. If \'k\' is the constant of proportionality, Em = 3k and Ew = 2k. Here, we need to apply the formula ∑(Mi Ei) D1 H1 / W1 = ∑(Mj Ej) D2 H2 / W2, where ∑(Mi Ei) = (6 x 3k) + (10 x 2k) ∑(Mj Ej) = (8 x 3k) + (6 x 2k) D1 = 15 days D2 = Number of days after increasing men and reducing women H1 = 6 hours H2 = 7 hours W1 = 150 km W2 = 210 km   So, we have 38k x 15 x 6 / 150 = 36k x D2 x 7 / 210 => 38k x 6 = 12k x D2 => D2 = 19 days Therefore, total days required to complete the work = 15 + 19 = 34 days
Question 8
A stadium was to be built in 1500 days. The contractor employed 200 men, 300 women and 750 robotic machines. After 600 days, 75% of the work was still to be done. Fearing delay, the contractor removed all women and 500 robotic machines. Also, he employed some more men having the same efficiency as earlier employed men. This led to a speedup in work and the stadium got built 50 days in advance. Find the additional number of men employed if in one day, six men, ten women and fifteen robotic machines have same work output.
Cross
1100
Cross
1340
Cross
1300
Tick
1140


Question 8-Explanation: 
Let the total work be 4 units.
=> Work done in first 600 days = 25% of 4 = 1 unit
=> Work done in next 850 days = 75% of 4 = 3 unit
Also, we are given that the daily work output of 6 men, 10 women and 15 robotic machines are same.
=> 6 Em = 10 Ew = 15 Er
=> Em : Ew : Er = 5 : 3 : 2, where \'Em\' is the efficiency of 1 man, \'Ew\' is the efficiency of 1 woman and \'Er\' is the efficiency of 1 robotic machine.
Therefore, ratio of efficiency of man, woman and robotic machine = 5:3:2.
If \'k\' is the constant of proportionality, Em = 5k, Ew = 3k and Er = 2k.
Here, we need to apply the formula
∑(Mi Ei) D1 H1 / W1 = ∑
(Mj Ej) D2 H2 / W2
, where
∑(Mi Ei) = (200 x 5k) + (300 x 3k) + (750 x 2k)
∑(Mj Ej) = (200 x 5k) + (m x 5k) + (250 x 2k), where \'m\' is the additional men employed
D1 = 600 days
D2 = 850 days
H1 = H2 = Daily working hours
W1 = 1 unit
W2 = 3 units
So, we have
3400k x 600 / 1 = (1500 + 5m)k x 850 / 3
=> 3400k x 1800 = (1500 + 5m)k x 850
=> 1500 + 5m = 7200
=> 5m = 5700
=> m = 1140
Therefore, additional men employed = 1140
Question 9
3 men and 4 women can complete a work in 10 days by working 12 hours a day. 13 men and 24 women can do the same work by working same hours a day in 2 days. How much time would 12 men and 1 women working same hours a day will take to complete the whole work?
Tick
4
Cross
6
Cross
8
Cross
10


Question 9-Explanation: 
Here, we need to apply the formula ∑(Mi Ei) D1 H1 / W1 = ∑(Mj Ej) D2 H2 / W2, where ∑(Mi Ei) = (3 x m) + (4 x w) ∑(Mj Ej) = (13 x m) + (24 x w), where \'m\' is the efficiency of each man and \'w\' is the efficiency of each woman D1 = 10 days D2 = 2 days H1 = 12 hours H2 = 12 hours W1 = W2 = Work to be done   So, we have (3m + 4w) x 10 x 12 = (13m + 24w) x 2 x 12 => 15m + 20w = 13m + 24w => 2m = 4w => m = 2w => m : w = 2 : 1 Therefore, ratio of efficiency of man and woman = 2 : 1 If the constant of proportionality be \'k\', Efficiency of each man = m = 2k Efficiency of each woman = w = k   Now, we re-apply the same formula. ∑(Mi Ei) D1 H1 / W1 = ∑(Mj Ej) D2 H2 / W2, where ∑(Mi Ei) = (3 x m) + (4 x w) ∑(Mj Ej) = (12 x m) + (1 x w) D1 = 10 days D2 = Days requires by 12 men and 1 woman H1 = 12 hours H2 = 12 hours W1 = W2 = Work to be done   So, we have (3m + 4w) x 10 x 12 = (12m + w) x D2 x 12 => 30m + 40w = (12m + w) x D2 => 60k + 40k = (24k + k) x D2 => 100k = 25k x D2 => D2 = 4 Therefore, 12 men and 1 woman would require 4 days to complete the work.
Question 10
600 men can make a road in 500 days. They start working together but after every hundred days, 50 men leave the work. Find the total time (in days) it takes to make the road.
Cross
600
Cross
550
Tick
650
Cross
750


Question 10-Explanation: 
600 men can make a road in 500 days. => Total work = 600 x 500 = 3,00,000 units Now, 600 men start working but after every hundred days, 50 men leave the work. => Work done in first 100 days = 600 x 100 = 60,000 units and total work done = 60,000 units => Work done in next 100 days = 550 x 100 = 55,000 units and total work done = 1,15,000 units => Work done in next 100 days = 500 x 100 = 50,000 units and total work done = 1,65,000 units => Work done in next 100 days = 450 x 100 = 45,000 units and total work done = 2,10,000 units => Work done in next 100 days = 400 x 100 = 40,000 units and total work done = 2,50,000 units => Work done in next 100 days = 350 x 100 = 35,000 units and total work done = 2,85,000 units => Work done in next 50 days = 300 x 50 = 15,000 units and total work done = 3,00,000 units Therefore, total time (days) taken to make the road = 650 days
There are 15 questions to complete.


  • Last Updated : 27 Sep, 2023

Share your thoughts in the comments
Similar Reads