GATE | GATE CS 2013 | Question 65

The current erection cost of a structure is Rs. 13,200. If the labour wages per day increase by 1/5 of the current wages and the working hours decrease by 1/24 of the current period, then the new cost of erection in Rs. is

(A)

16,500

(B)

15,180

(C)

11,000

(D)

10,120

Answer