Job Assignment Problem using Branch And Bound
Let there be N workers and N jobs. Any worker can be assigned to perform any job, incurring some cost that may vary depending on the work-job assignment. It is required to perform all jobs by assigning exactly one worker to each job and exactly one job to each agent in such a way that the total cost of the assignment is minimized.
Let us explore all approaches for this problem.
Solution 1: Brute Force
We generate n! possible job assignments and for each such assignment, we compute its total cost and return the less expensive assignment. Since the solution is a permutation of the n jobs, its complexity is O(n!).
The optimal assignment can be found using the Hungarian algorithm. The Hungarian algorithm has worst case run-time complexity of O(n^3).
Solution 3: DFS/BFS on state space tree
A state space tree is a N-ary tree with property that any path from root to leaf node holds one of many solutions to given problem. We can perform depth-first search on state space tree and but successive moves can take us away from the goal rather than bringing closer. The search of state space tree follows leftmost path from the root regardless of initial state. An answer node may never be found in this approach. We can also perform a Breadth-first search on state space tree. But no matter what the initial state is, the algorithm attempts the same sequence of moves like DFS.
Solution 4: Finding Optimal Solution using Branch and Bound
The selection rule for the next node in BFS and DFS is “blind”. i.e. the selection rule does not give any preference to a node that has a very good chance of getting the search to an answer node quickly. The search for an optimal solution can often be speeded by using an “intelligent” ranking function, also called an approximate cost function to avoid searching in sub-trees that do not contain an optimal solution. It is similar to BFS-like search but with one major optimization. Instead of following FIFO order, we choose a live node with least cost. We may not get optimal solution by following node with least promising cost, but it will provide very good chance of getting the search to an answer node quickly.
There are two approaches to calculate the cost function:
- For each worker, we choose job with minimum cost from list of unassigned jobs (take minimum entry from each row).
- For each job, we choose a worker with lowest cost for that job from list of unassigned workers (take minimum entry from each column).
In this article, the first approach is followed.
Let’s take below example and try to calculate promising cost when Job 2 is assigned to worker A.
Since Job 2 is assigned to worker A (marked in green), cost becomes 2 and Job 2 and worker A becomes unavailable (marked in red).
Now we assign job 3 to worker B as it has minimum cost from list of unassigned jobs. Cost becomes 2 + 3 = 5 and Job 3 and worker B also becomes unavailable.
Finally, job 1 gets assigned to worker C as it has minimum cost among unassigned jobs and job 4 gets assigned to worker D as it is only Job left. Total cost becomes 2 + 3 + 5 + 4 = 14.
Below diagram shows complete search space diagram showing optimal solution path in green.
Complete Algorithm:
/* findMinCost uses Least() and Add() to maintain the
list of live nodes
Least() finds a live node with least cost, deletes
it from the list and returns it
Add(x) calculates cost of x and adds it to the list
of live nodes
Implements list of live nodes as a min heap */
// Search Space Tree Node
node
{
int job_number;
int worker_number;
node parent;
int cost;
}
// Input: Cost Matrix of Job Assignment problem
// Output: Optimal cost and Assignment of Jobs
algorithm findMinCost (costMatrix mat[][])
{
// Initialize list of live nodes(min-Heap)
// with root of search tree i.e. a Dummy node
while (true)
{
// Find a live node with least estimated cost
E = Least();
// The found node is deleted from the list
// of live nodes
if (E is a leaf node)
{
printSolution();
return;
}
for each child x of E
{
Add(x); // Add x to list of live nodes;
x->parent = E; // Pointer for path to root
}
}
}
Below is the implementation of the above approach:
C++
// Program to solve Job Assignment problem
// using Branch and Bound
#include <bits/stdc++.h>
using namespace std;
#define N 4
// state space tree node
struct Node
{
// stores parent node of current node
// helps in tracing path when answer is found
Node* parent;
// contains cost for ancestors nodes
// including current node
int pathCost;
// contains least promising cost
int cost;
// contain worker number
int workerID;
// contains Job ID
int jobID;
// Boolean array assigned will contains
// info about available jobs
bool assigned[N];
};
// Function to allocate a new search tree node
// Here Person x is assigned to job y
Node* newNode(int x, int y, bool assigned[],
Node* parent)
{
Node* node = new Node;
for (int j = 0; j < N; j++)
node->assigned[j] = assigned[j];
node->assigned[y] = true;
node->parent = parent;
node->workerID = x;
node->jobID = y;
return node;
}
// Function to calculate the least promising cost
// of node after worker x is assigned to job y.
int calculateCost(int costMatrix[N][N], int x,
int y, bool assigned[])
{
int cost = 0;
// to store unavailable jobs
bool available[N] = {true};
// start from next worker
for (int i = x + 1; i < N; i++)
{
int min = INT_MAX, minIndex = -1;
// do for each job
for (int j = 0; j < N; j++)
{
// if job is unassigned
if (!assigned[j] && available[j] &&
costMatrix[i][j] < min)
{
// store job number
minIndex = j;
// store cost
min = costMatrix[i][j];
}
}
// add cost of next worker
cost += min;
// job becomes unavailable
available[minIndex] = false;
}
return cost;
}
// Comparison object to be used to order the heap
struct comp
{
bool operator()(const Node* lhs,
const Node* rhs) const
{
return lhs->cost > rhs->cost;
}
};
// print Assignments
void printAssignments(Node *min)
{
if(min->parent==NULL)
return;
printAssignments(min->parent);
cout << "Assign Worker " << char(min->workerID + 'A')
<< " to Job " << min->jobID << endl;
}
// Finds minimum cost using Branch and Bound.
int findMinCost(int costMatrix[N][N])
{
// Create a priority queue to store live nodes of
// search tree;
priority_queue<Node*, std::vector<Node*>, comp> pq;
// initialize heap to dummy node with cost 0
bool assigned[N] = {false};
Node* root = newNode(-1, -1, assigned, NULL);
root->pathCost = root->cost = 0;
root->workerID = -1;
// Add dummy node to list of live nodes;
pq.push(root);
// Finds a live node with least cost,
// add its childrens to list of live nodes and
// finally deletes it from the list.
while (!pq.empty())
{
// Find a live node with least estimated cost
Node* min = pq.top();
// The found node is deleted from the list of
// live nodes
pq.pop();
// i stores next worker
int i = min->workerID + 1;
// if all workers are assigned a job
if (i == N)
{
printAssignments(min);
return min->cost;
}
// do for each job
for (int j = 0; j < N; j++)
{
// If unassigned
if (!min->assigned[j])
{
// create a new tree node
Node* child = newNode(i, j, min->assigned, min);
// cost for ancestors nodes including current node
child->pathCost = min->pathCost + costMatrix[i][j];
// calculate its lower bound
child->cost = child->pathCost +
calculateCost(costMatrix, i, j, child->assigned);
// Add child to list of live nodes;
pq.push(child);
}
}
}
}
// Driver code
int main()
{
// x-coordinate represents a Worker
// y-coordinate represents a Job
int costMatrix[N][N] =
{
{9, 2, 7, 8},
{6, 4, 3, 7},
{5, 8, 1, 8},
{7, 6, 9, 4}
};
/* int costMatrix[N][N] =
{
{82, 83, 69, 92},
{77, 37, 49, 92},
{11, 69, 5, 86},
{ 8, 9, 98, 23}
};
*/
/* int costMatrix[N][N] =
{
{2500, 4000, 3500},
{4000, 6000, 3500},
{2000, 4000, 2500}
};*/
/*int costMatrix[N][N] =
{
{90, 75, 75, 80},
{30, 85, 55, 65},
{125, 95, 90, 105},
{45, 110, 95, 115}
};*/
cout << "\nOptimal Cost is "
<< findMinCost(costMatrix);
return 0;
}
Python
import heapq
import copy
N = 4
# State space tree node
class Node:
def __init__(self, x, y, assigned, parent):
self.parent = parent
self.pathCost = 0
self.cost = 0
self.workerID = x
self.jobID = y
self.assigned = copy.deepcopy(assigned)
if y != -1:
self.assigned[y] = True
# Custom heap class with push and pop functions
class CustomHeap:
def __init__(self):
self.heap = []
def push(self, node):
heapq.heappush(self.heap, (node.cost, node))
def pop(self):
if self.heap:
_, node = heapq.heappop(self.heap)
return node
return None
# Function to allocate a new search tree node
# Here Person x is assigned to job y
def new_node(x, y, assigned, parent):
return Node(x, y, assigned, parent)
# Function to calculate the least promising cost
# of node after worker x is assigned to job y.
def calculate_cost(cost_matrix, x, y, assigned):
cost = 0
# to store unavailable jobs
available = [True] * N
# start from the next worker
for i in range(x + 1, N):
min_val, min_index = float('inf'), -1
# do for each job
for j in range(N):
# if job is unassigned
if not assigned[j] and available[j] and cost_matrix[i][j] < min_val:
# store job number
min_index = j
# store cost
min_val = cost_matrix[i][j]
# add cost of next worker
cost += min_val
# job becomes unavailable
available[min_index] = False
return cost
# Comparison object to be used to order the heap
class Comp:
def __init__(self, node):
self.node = node
def __lt__(self, other):
return self.node.cost > other.node.cost
# Print Assignments
def print_assignments(min_node):
if min_node.parent is None:
return
print_assignments(min_node.parent)
print("Assign Worker {} to Job {}".format(chr(min_node.workerID + ord('A')), min_node.jobID))
# Finds minimum cost using Branch and Bound
def find_min_cost(cost_matrix):
# Create a priority queue to store live nodes of the search tree
pq = CustomHeap()
# initialize heap to dummy node with cost 0
assigned = [False] * N
root = new_node(-1, -1, assigned, None)
root.pathCost = root.cost = 0
root.workerID = -1
# Add dummy node to list of live nodes;
pq.push(root)
# Finds a live node with least estimated cost,
# add its children to the list of live nodes and
# finally deletes it from the list.
while True:
# Find a live node with least estimated cost
min_node = pq.pop()
# i stores the next worker
i = min_node.workerID + 1
# if all workers are assigned a job
if i == N:
print_assignments(min_node)
return min_node.cost
# do for each job
for j in range(N):
# If unassigned
if not min_node.assigned[j]:
# create a new tree node
child = new_node(i, j, min_node.assigned, min_node)
# cost for ancestors nodes including the current node
child.pathCost = min_node.pathCost + cost_matrix[i][j]
# calculate its lower bound
child.cost = child.pathCost + calculate_cost(cost_matrix, i, j, child.assigned)
# Add child to list of live nodes;
pq.push(child)
# Driver code
if __name__ == "__main__":
# x-coordinate represents a Worker
# y-coordinate represents a Job
cost_matrix = [
[9, 2, 7, 8],
[6, 4, 3, 7],
[5, 8, 1, 8],
[7, 6, 9, 4]
]
# Optimal Cost
optimal_cost = find_min_cost(cost_matrix)
if optimal_cost is not None:
print("\nOptimal Cost is {}".format(optimal_cost))
else:
print("\nNo optimal solution found.")
Output :
Assign Worker A to Job 1
Assign Worker B to Job 0
Assign Worker C to Job 2
Assign Worker D to Job 3
Optimal Cost is 13
Time Complexity: O(M*N). This is because the algorithm uses a double for loop to iterate through the M x N matrix.
Auxiliary Space: O(M+N). This is because it uses two arrays of size M and N to track the applicants and jobs.